PROJECT PROFILE
Historic Registered Marin County Civic Center

ORIGINAL BUILDING DESIGNER
Frank Lloyd Wright

BUILDING CONSTRUCTED:
Admin and Dome 1962
Hall of Justice 1969

BUILDING OWNER:
County of Marin, California

APPROXIMATE ROOF SIZE:
220,000 Square feet

PROJECT PHOTOGRAPHS
TRS - Chris Nelson & John A. Goveia

REROOF CONTRACT:
$1,350,000.00
$150,000.00 - Skylight Repairs

REROOF PERIOD:
June 1999 - November 1999

OWNER REPRESENTATIVE:
County of Marin
J. Mike Bianchi, P.E.

ROOF CONSULTANT:
Technical Roof Services, Inc.
John A. Goveia & Chris Nelson
CADD by Brett Brogan & Paula Rizzotti

SKYLIGHT CONSULTANT:
Skyline Engineering, Bryan Schalesky, P.E.

ENVIRONMENTAL CONSULTANT:
Kellco Services, Inc.
Tim Cannard, CAC, REA

ROOF CONTRACTOR:
D.C. Taylor, Inc.
Greg Special & Mark Wilson
Erin Easter & Phil Brambila

ENVIRONMENTAL CONTRACTOR:
R.B. Construction, Inc.
Ron Barber & Cory Suppes

CONCRETE REPAIR CONTRACTOR:
Lotus General Contractor's, Inc.

METAL RESTORATION ANODIZING CONTRACTOR:
Lewis Restoration

ROOF COATING SYSTEM MANUFACTURER:
United Coatings
Charlie Van Gelder & Lance Murphy

August 1999 Blue Coating on Dome